GDW Engineering was successful in being awarded a lump sum high and low voltage design and construct project at Moolarben Coal near Mudgee NSW. 

The scope involved at a high level:

  • Two kilometer's of 11KV HV cable trenching, installation and backfill
  • Full electrical design drawings for the package
  • Engineering studies including arc flash, protection and earthing.
  • Procurement of MCC, Switch room, LCS’s, instruments and cable
  • High voltage terminations and QA
  • Low termination and QA
  • Installation and commissioning of schneider RM6 RMU’s and 11/415V Wilson transformers
  • Installation and commissioning of schneider RM6 RMU’s and 11/415V Wilson transformers
  • Risk assessment facilitation
  • Lighting design and installation
  • Instrumentation calibrations
  • MDR and handover package
  • Operator training
Latest News & Projects
View All
Communications Tower

OC3 Comms Tower

Port of Newcastle

ESG Lighting Upgrade Project Stage 1

MACH ENERGY High Wall Dam
Industrial Electrical, Project & Construction Management

Electrical Construction and Instrumentation Project

CHPP Operational Support & Maintenance
Industrial Electrical, Switchroom, MCCs and Switchboards, Project & Construction Management, Hazardous Areas & Instrumentation

Coal Mine Project, Infrastructure, Prep and Handling Plant Electrical Support Services

Kurri Kurri Lateral Pipeline - E&I Installation
Industrial Electrical, Project & Construction Management, Switchroom, MCCs and Switchboards, Hazardous Areas & Instrumentation

Supply and installation as the E&IC contractor for the Kurri Kurri Lateral Pipeline Project feeding the new Hunter Power Project. Snowy Hydro has constructed a gas fired power station with a capacity of 750 Mega Watts. GDW were responsible for the Electrical and Instrumentation, to AS3000, 3008 and 60079 compliance, component of the pipeline that feeds the new power station.